Bath Quays Links

Construction update

Construction of the Green Park Road (A367) scheme is ongoing and aims to complete by 20 November 2026.

Improvement works at Lower Bristol Road (A36) began in January 2026 as part of the Bath Quays Links (BQL) project. The aim of this scheme is to make walking, wheeling and cycling easier and more enjoyable in central Bath. You can find out more about the Lower Bristol Road (A36) project aims here.

From May 2026, due to subcontractor issues, we decided to pause construction and appoint a new subcontractor.

The existing pedestrian island opposite Newark Works was removed as part of the initial works. We appreciate this has affected a well-used walking route. When works resume, a new controlled crossing will be installed as part of the scheme.

We're committed to ensuring final works are delivered promptly and to the required standard. When the work is booked in to start again, we will update our project web page with the new construction timetable.

Thank you for your patience as we work to complete this project.

 

Use this page to find out about the proposed improvements to the walking, wheeling and cycling links near Bath Quays Bridge.

Project and strategy context

We aim to provide more travel choices for everyone. As part of our Corporate Strategy, we want to make walking, wheeling, and cycling safer, more convenient and accessible, while helping to reduce congestion, improve air quality and promote healthy lifestyles.

Bath Quays Links (BQL) is an initiative designed to help make walking, wheeling and cycling easier, and more enjoyable, in central Bath. It is one of several CRSTS (City Region Sustainable Transport Settlements) projects being developed in Bath. It will work alongside other transport strategy initiatives in the city, to support our community's travel choices.

Its focus is the walking and cycling bridge across the River Avon which opened in 2022, providing improved access for the Quays developments and into other areas of the city and beyond.

Previous public engagement

We previously consulted on proposed active travel facilities to connect the new bridge at the Bath Quays development into the existing network in 2022.

Upcoming works

Select a road from the list below to read in detail what we plan to do:

Lower Bristol Road (A36) 

We're providing:

  • new cycle lanes on both sides of the road between Westmoreland Road and Oak Street, including bus stop bypasses to route cycles behind bus stops.
  • a new puffin crossing for pedestrians east of Westmoreland Road/Riverside Road.
  • conversion of the existing pedestrian crossing next to Aquila Court into a toucan crossing for both pedestrians and cycles.
  • improvements to the road and footways between Westmoreland Road and Oak Street with removal of steep footway gradients and drainage improvements to reduce flooding.

This scheme entered construction in January 2026 and was paused in May 2026 due to subcontractor issues.

We're committed to ensuring final works are delivered promptly and to the required standard. When the work is booked in to start again, we will update our project web page with the new construction timetable.

Green Park Road (A367) 

We're providing:

  • a new two-way cycle lane on the west side of Green Park Road. It will be at the same level as the carriageway but separated by kerbs on both sides, providing a safe environment for cycling and maintaining a footway for pedestrians. A bus stop bypass will route cycles behind the northbound bus stop.
  • a new zebra crossing adjacent to Bath Quays Bridge
  • reallocation of the existing zebra crossing near Green Park House

The scheme will integrate with proposals for a two-way cycle lane on the west side of Charles St (part of the Bath City Centre project) and proposals for a two-way cycle lane on the west side of Queens Square (part of the Bath Walking, Wheeling and Cycling project).

The construction of this scheme is ongoing and aims to complete by 20 November 2026.

View the proposals on a map

Our current proposals affect the area highlighted in blue on this map of the Bath Cycle Network.

We are constantly working to create and improve the network to make it easier and safer to get around the city using modes of active travel.

Map of section 1 of the proposed improvements to Bath's cycle network.

The graphics below show an illustration of what the route will look like once complete, for Green Park Road (top) and Lower Bristol Road (below).

a graphic showing the improvements being made to Lower Bristol Road including widening of pavements, new crossings, and cycle paths.

a graphic image showing the new segregated cycle route on Green Park Road and the location of new zebra crossings. The route links to the pedestrian bridge at Bath Quays.

Proposed construction dates

Construction of Bath Quays Links began in October 2025. Efforts have been made to ensure disruption is kept to a minimum. There will be traffic management in place such as traffic lights.

See a graphic of the traffic management for this project.

Site namePlanned StartEstimated DurationWorks SummaryStatus
Lower Bristol Road12 January 20269 monthsNew cycle lanes, bus stop bypasses, new/improved pedestrian/cycle crossings, improved roads and pavements.Paused
Green Park Road20 October 202513 monthsNew cycle lane, new zebra crossing, improvement of existing zebra crossings.Ongoing

Key project aims

  • Providing safe, accessible and enjoyable walking, wheeling and cycling routes
  • Adding walking infrastructure to enable active travel
  • Increasing safety for those choosing sustainable methods of transport
  • Linking up to existing and planned cycling networks in the city

How Bath Quays Links connect to the wider network

The new scheme elements offer the following links into existing or planned networks:

Why walking and cycling are important

We need to make walking, wheeling and cycling the natural choice for a lot more of our journeys. Currently, over a third of car trips across Bath and North East Somerset are less than 5km.
The importance of walking, wheeling, and cycling, or ‘active travel’ as an affordable and accessible mode of transport has become increasingly apparent over recent years.
The benefits of active travel are extensive - from improving air quality to ensuring healthier places and people. By enabling more travel options, we can optimise road space for all.

Active Travel Masterplan

The routes are part of our emerging Active Travel Masterplan, a comprehensive plan that sets out the existing and future network of active travel infrastructure. 

It aims to enable walking, cycling, and other forms of active travel, ensuring safer, healthier, and more accessible transport options for everyone. It will support all types of journeys, including commuting, education, leisure, and tourism.

View the Active Travel Masterplan page to find out more.

Project timeline

Dates and project stages
DateStage
July to Aug 2022Public consultation on draft proposals
2023 to 2024Refining of proposals and scheme development
Jan 2025Complete detailed design
April 2025 (complete)Submission of Full Business Case to West of England Combined Authority
Summer 2025 (complete)Full Business Case approval
Spring/Summer 2025 (complete)TRO (Traffic Regulation Order) public consultation
Autumn 2025Construction starts