Use this page to stay up to date with what’s happening with A36 Beckford Road, the canal tunnel and towpath following a structural issue.
Background
The A36 Beckford Road crosses over the Kennet & Avon canal tunnel at the north end of Sydney Gardens in Bath. Here the road is supported by a stone arch tunnel known as Bath No.1 Canal Tunnel. The tunnel has been affected by a structural issue that was identified during planned works to improve walking and cycling links to Bathwick St Mary Primary School, King Edward's School, Sydney Gardens, the Holburne Museum, Great Pulteney Street and the canal.
The canal tunnel is an historic structure and repairing it is a complex job. The council, Canal & River Trust, Historic England and the contractor are working closely together to carry out further surveys, investigation and design work and secure the necessary approvals before permanent repairs can begin.
It is anticipated that this work could continue into 2027.
Update 18 November
We are continuing to monitor traffic on the A36 Beckford Road while temporary traffic management remains in place following the structural issue affecting Bath No.1 Canal Tunnel.
The majority of the time, traffic is moving well through the temporary signals. However, we recognise that there are periods during the day when congestion can become heavy and journeys are affected.
Our traffic engineers are monitoring these periods and considering all options to help traffic move as effectively as possible. This includes manual operation of the signals at peak times when appropriate and looking at whether the actual on site length of the temporary closure on site can be reduced.
At present, we do not consider there is a requirement to divert traffic away from Beckford Road or introduce wider traffic restrictions, but we will continue to monitor the situation and keep this under review.
Safety remains our priority. We continue to work closely with the Canal & River Trust, Historic England and our contractor on the surveys, investigations and design work needed before permanent repairs to the historic tunnel can begin. The complexity of the structure means this work could continue into 2027.
Update 4 November 2026
Investigations and assessments are continuing, including the following:
- Review historic and inspection records.
- Undertaking laser scanning, photographic, heritage, and structural surveys to establish the full picture to inform the design process.
- Confirm what consents are needed between the main stakeholders including the council and the Canal & River Trust.
- Implement any temporary measures considered necessary to protect the structure and maintain public safety.
- Carry out regular engineering inspections to monitor the structure condition.
- Working together for the safe passage of boats.
The council is not yet able to confirm any potential diversion routes. Please check this website for updates.
Update 12 October 2026
A structural issue affecting a tunnel beneath the A36 Beckford Road in Bath, which was identified during planned works to improve walking and cycling routes.
As a precaution, the canal and adjacent towpath at the north end of Sydney Gardens have been closed to boats and pedestrians. An eastbound one-lane road closure is in place as engineers continue to assess the situation.
Thank you to the residents who alerted us promptly. Public safety remains our priority, and we apologise for any inconvenience.
Works on the A36 are expected to be delayed as a result. When information
becomes available it will be updated on this website.