Since 2020 we have held a series of public engagements to identify issues and gather people’s ideas for improvements.
- Autumn 2020: we asked residents across the district how they felt about LNs. 48 communities then applied to become a LN, via ward councillors
- Spring 2021: we prioritised 15 areas where development of LNs could start.
- Winter 2021/22: we asked for feedback on what was good about these areas, what transport-related issues people experienced, and what improvements would make the most impact.
- Spring/Summer 2022: we held a series of co-design workshops in each area to identify and prioritise the measures residents would like to see included in draft designs (see below).
- Autumn 2022: we launched ongoing consultations for a minimum of six months on three through-traffic restriction trials in three areas (ahead of the wider programme).
- Spring 2024: we are proposing to fast track five new trials with ongoing public consultation for a minimum of six months.
- Spring 2024: we will engage the public on the overall designs for each of the LN areas once the full business case is approved.
View the project development timeline for more information and to read our consultation output reports.
View more information on the development of each LN and the outcome of the co-design workshops