We are making improvements in Royal Victoria Park to make it safer and easier for you to get around.
The improvements include better pavements, crossings and lighting, as well as a proposal for a family-friendly cycle lane along the southern and western park roads.
Construction began on 19 October 2026 with the installation of new pavements and heritage-style lighting columns. See our construction timetable and traffic management plan for more details.
We expect construction to continue until mid-March 2027. We are delivering the work in phases to reduce disruption and maintain access to park facilities.
We secured government funding for the scheme; however, this money can only be spent on active travel improvements (walking, wheeling and cycling) and public transport. It can't be used for other schemes in the park or for other things like highway repairs and fixing potholes.
During the first phase, short-stay visitor parking is available on the northern and eastern park roads, Park Lane and Weston Road. The access road from Park Lane remains open, with parking available on one side, but we expect this to close from 2 November for approximately two weeks.
Pedestrian footways and crossings are protected around the works, and businesses are open as usual.
View or download a map of the proposed Royal Victoria Park improvements
Improvements we are making
The project proposals include:
- heritage-style, energy-efficient lighting through the south-west section of the park to make the park feel safer
- resurfaced pavements
- four new raised pedestrian crossings through the south of the park
- a new raised zebra crossing on Park Lane
- a new raised crossing at the top of the north-west access road
- six additional accessible parking bays, doubling the number in the southern area of the park
- a family-friendly, segregated contraflow cycle lane between Park Lane and the Victorian Obelisk
Royal Victoria Park improvements - some questions and answers
Discover the facts about the improvements we are making at Royal Victoria Park, and some of the incorrect information that is being shared.
We secured government funding for the scheme, this money however can only be spent on active travel for walking, wheeling, cycling, and public transport. It can't be used for other schemes in the park or highways repairs like potholes.
Royal Victoria Park contains roads to which the public has access and in legal terms these can be treated as highways or roads for traffic regulation purposes, even if they are not adopted highway maintainable at public expense. Under the Road Traffic Regulation Act 1984, the council has powers to make Traffic Regulation Orders on highways and on other roads to which the public has access. As the roads within Royal Victoria Park are publicly accessible and operate as roads in the ordinary sense, the council is satisfied that the necessary legal powers exist to make and implement the relevant Traffic Regulation Orders associated with the scheme. Other Traffic Regulation Orders made under the same process have been in place within Royal Victoria Park since 2009.
Following the making of one of the Traffic Regulation Orders for Royal Victoria Park which relates to a cycle lane, it came to our attention that an objection had not been considered by the decisionmaker due to a technical and administrative oversight. We are putting this right by reviewing the decision, with the previously omitted objection considered alongside all other objections received, before a new decision is made. Meanwhile work on footways and lighting, which were approved under separate Traffic Regulation Orders, is progressing in the park.
Planning permission was not required as the works are deemed permitted development with no requirement for any heritage-based approvals/consents and will not physically impact on any listed structures within the park.
- We have not ignored the objections. The scheme was revised in response to people’s concerns, and the final decision balances access, safety, parking and the need for better walking, wheeling and cycling connections.
- The council has listened carefully. Consultation is not a referendum. Its purpose is to identify concerns, test the proposals and help the council reach a properly informed decision.
- We have made changes. The original scheme was changed following public feedback. The existing one-way vehicle entrance from Park Lane will remain open, parking will remain on all sides of the park, the cycling route will use flexible separators rather than kerbs, and the scheme now includes significant improvements for pedestrians and people with reduced mobility.
- The statutory responses, including 219 objections or partial objections to the cycle lane and 85 objections or partial objections to the parking restrictions, were fully considered before the decision was taken. 2000 residents surrounding the park were told directly about the statutory consultation by letter and it was promoted in the council’s newsroom and social media platforms.
During the early phase of construction, we needed to temporarily restrict pedestrian access at two entry points along Park Lane. This was due to safety concerns as heavy machinery was moved into position and works to remove pavement surface material took place. Both access points are now open.
- 177 of the 287 parking bays are remaining within the park itself, excluding Royal Avenue. This is sufficient to meet demand for parking within the park itself on the busiest days the council surveyed.
- Parking will remain on all sides of the park, including along the southern and south-western carriageways near the play park and other amenities.
This is supplemented by:
- around 74 short-stay spaces on Weston Road, with the first hour free.
- existing short-stay parking on Park Lane, free for up to three hours.
- parking on Royal Avenue for short-stay visitors and permit holders.
Once the scheme is in place, and including the new Weston Road provision, overall capacity is expected to be approximately 87% of the current level.
- Six new disabled bays would be located near amenities (3 located on southwest carriageway and three on Royal Avenue).
- A total of 20 disabled parking bays would then be available within the park.
Parking surveys indicate that once the scheme is in place, the park and nearby short-stay bays can accommodate demand without visitors having to resort to parking on nearby residential streets or in residents parking zones. The council will monitor how the arrangements work.
The new Weston Road short stay bays are particularly relevant. Parking here was previously unrestricted, meaning they could be occupied for long periods by commuters. Their conversion to short-stay parking should make them more useful and more regularly available to park visitors. The council will monitor parking behaviour once the new arrangements are established.
These measures should help people using wheelchairs, mobility aids and families using buggies and prams.
The wider scheme also includes raised crossings level with the pavements, resurfaced pavements, better lighting, clearly defined crossing points and continued vehicle access through the north-west entrance.
- The scheme retains vehicle access, increases accessible parking and removes physical barriers at key crossing points for people with mobility aids.
- Accessible parking close to key amenities is increasing, not decreasing.
- Within the western and southern parts of the park, the number of accessible bays will rise from six to nine, and regular short stay parking bays are still available along these routes.
- Three further accessible bays will be created on Royal Avenue, giving six additional bays across these locations. Existing accessible parking near the Botanic Gardens is also being retained.
Families will still be able to drive into and park within Royal Victoria Park. Parking remains available along the southern and south-western carriageways, including near the play park, toilets and café. Additional accessible bays near key amenities also support families.
Some visitors may occasionally have to park further from their preferred destination. However, the aim is not to require every visitor to park on the northern side of the park. Parking remains distributed around the park, while improved pavements, lighting and raised crossings will make onward journeys safer and easier.
We are working with our tree specialist to make sure the trees are protected as we carry out these works. We have changed the excavation methods to make sure this is the case following some damage to tree roots during initial excavation works. None of the trees close to the works have Tree Protection orders.
No. We were alerted to the possibility of a badger sett in close proximity to our works during the early stages of construction. An ecologist has attended the site to assess this possibility and determined no badger setts are affected by our works. An identified badger sett within the Botanical Gardens will not be affected by the proposed scheme works and no disturbance to the badgers is anticipated. The badger sett does not present a constraint to the scheme.
Long-term parking arrangements
Parking will still be available throughout the park, with 177 spaces available. We are doubling the number of accessible parking bays in the south of the park to 12.
We will relocate six existing accessible bays from the northern side of the southern park road to the southern side, closest to the play park.
Short-stay parking, with the first hour free, will remain available on all sides of the park and on the north-west access road.
There are also 74 new short-stay spaces on Weston Road, with the first hour free. Existing short-stay parking on Park Lane is free for up to 3 hours.
Construction programme and traffic management
We will update the construction programme as dates and arrangements for new phases are confirmed.
Construction will generally take place from Monday to Friday, 7.30am to 5pm.
Traffic management measures and parking restrictions will remain in place outside these hours where needed for safety.
Phase one: 20 October to 2 November 2026
During the first phase we:
started to install new paving along the western side of the Park Lane access road
started to install new paving along the western and southern park roads near the play park
prepared the site for the installation of new heritage-style lighting columns.
Phase two: 2 November to 16 November 2026
During the second phase we will:
continue works outlined in phase 1 to install new paving along the western side of the Park Lane access road
install a zebra crossing in Park Lane, near the northwest access road to Royal Victoria Park
install a raised pedestrian crossing at the northwest access route and make improvements to pavements
During phase two these restrictions will be in place 24 hours a day.
The access road from Park Lane, western and southern park roads near the play park will be closed to vehicles.
All parking within the closure area will be suspended.
Due to the access road from Park Lane being closed, all parking along the northern park road will also be suspended.
The western footways along the access road and affected park roads will be closed.
Access during phase two
We will maintain access in the following ways:
The access road from Weston Road will remain open, with parking retained on the eastern side of the park.
Drivers and cyclists can continue to follow the clockwise one-way route around the park from the Weston Lane entrance.
Drivers and cyclists can exit via the Victorian Obelisk
Pedestrian access is maintained along at least one of the Park Lane access road pavements. All other pedestrian access points will remain open.
Access to the play area and park amenities will be maintained via protected pedestrian footways on the eastern side of South Road, with dedicated crossing points provided.
Parking is available along the eastern road of the park.
Parking during phase 2
Short-stay visitor parking will remain available at:
the eastern side of the park
Park Lane, which is free for up to 3 hours
Royal Avenue, including the accessible parking bays
The new parking bays on Weston Road
Access to businesses and amenities
Pedestrian footways through the park and play area will be protected throughout the work, and dedicated crossings are provided.
We and our contractor are working with businesses in the park so that deliveries and essential vehicle access can continue.
Site supervisors will assist when access is needed for maintenance vehicles, deliveries or other operational requirements.
If you have questions about access for deliveries or maintenance, contact the project team using the details at the end of this page.
Events in the park
Events in the park will continue as planned.
Temporary restrictions on vehicle movements and parking will be in place in some areas while the work is underway.
If you are attending an event, consider using public transport and allow plenty of time for your journey.
If you are organising an event and have questions about access during the work, contact the project team.
Future phases
The work will continue in phases to reduce disruption and maintain access through the park.
We will publish information about future phases and traffic management arrangements before work begins in each area.
Other improvements in the park
Restoring the historic ponds
Work is progressing on the restoration of Royal Victoria Park’s historic ponds.
We have removed silt and the damaged pond liner to help restore a reliable water supply and improve conditions for wildlife. We will consult on the long-term future of the ponds later in autumn 2026.
Find out more about the Royal Victoria Park ponds project
Golf and footgolf
We are also working to secure the long-term future of golf and footgolf following the operator's decision to cease trading. Excel Tennis Ltd, which operates the tennis courts and Treetop Café, is running golf and footgolf sessions at weekends during October while we complete the appointment of a new long-term operator. We expect a new operator to be in place from November.
We expect a new operator to be in place from November 2026.
Contact the project team
Contact the project team if:
- you have a question about the project
- you need to discuss access for business, delivery or maintenance vehicles
- you need this information in an alternative format.
You can email BWWCL@bathnes.gov.uk or call 01225 394025.
Visit our Bath, Walking Wheeling and Cycling scheme page to read about the background to the Royal Victoria Park improvements