Carriageway Resurfacing

A Map showing all resurfacing sites for the 2017 /18 period can be found at the link below:

Map of 2018/19 Resurfacing Sites

The annual highways structural maintenance programme is funded from capital expenditure sourced through:

  • Local Transport Plan Maintenance Block Funding from Central Government

  • Section 31 Grant Funding

  • Council Capital Funding

This annual programme of works is segregated into the improvement of a variety of highway assets as follows:

All the works included in the carriageway and footway/footpath programmes are subject to rigorous prioritisation and options appraisal utilising best asset management practice such that optimal value for money works are carried out taking into account local issues. Significant work is done in terms of machine and visual surveys, analysis of revenue expenditure and safety inspection records all assessed against network hierarchy in determining priority and treatment to be applied.

Our Street Work team work both internally with other departments and externally with public utility companies to co-ordinate works across our highway network and those of neighbouring authorities.

Carriageway Improvement Works

Surfacing and Reconstruction Works

These works traditionally involve overlaying or inlaying large areas of carriageway and where necessary carrying out deeper reconstruction on isolated areas where significant structural failure is evident. Coring investigation work is undertaken beforehand to fully assess the work required.

The overlaying of an existing carriageway will involve treating the surface with a tack coat on to which a new surface course is applied. Inlaying is more intrusive as it involves planing and milling of the existing surface followed by the application of tack coat and new surface course. With both processes there is the need to adjust the height and level of all ironwork along the affected length.

Typical surface course materials are Asphalt Concrete (bitumen macadam), Hot Rolled Asphalt or another selected proprietary product selected to meet local site conditions.

Due to the health and safety of both highway users and operatives carrying out the works this type of work in most cases necessitates a road closure for the duration. To minimise disruption to highway users these works can on occasion be carried out overnight and on weekends. School holidays and local events are considered in the planning and programming of these projects.

Surface Dressing

Surface dressing is a simple and highly cost-effective method of repairing the road surface, which can prevent much more expensive work being needed later. It allows us to maintain a high quality road network on a finite budget.

The process involves spraying the road surface with a coating of hot liquid bitumen, known as a binder. The coating is then covered with clean crushed stone chippings, which are rolled into the bitumen to form a water-resistant, protective layer, which improves skid resistance.

This type of work can only be done in the spring and summer months, when the weather is warm and dry, as the bitumen will not stick to the road in cold or wet conditions. This is a mobile operation and is an efficient process that allows us to reduce the time on site, thus causing minimum disruption to local highway users. These works are normally only carried out on the rural roads of our Network as using hot applied binder is not suitable within urban areas.

Micro Asphalt

Micro Asphalt Surfacing consists of bitumen emulsion and aggregate slurry which is laid cold by a specialised machine. The surfacing seals the top surface and improves skid resistance not dissimilar to Surface Dressing.

This type of surfacing is widely used in the urban areas of our Network. The finished surface has low noise characteristics and good riding qualities; as this is a mobile operation it is an efficient process that allows us to reduce the time on site thus causing minimum disruption to local highway users.

Sites and dates of resurfacing are shown below. Any constructive comments or concerns are welcome in order to help us improve our methods of working and public relations. These comments can be sent by email to Highways@bathnes.gov.uk or by a phone call to Council Connect on 01225 39 40 41 (in each case asking for the information to be forwarded to Andy Higginson in the Highway Maintenance Team).

If you would like more information regarding the Carriageway Resurfacing please email: Highways@bathnes.gov.uk or call Council Connect of 01225 39 40 41.

All Surfacing Sites for 2015 / 2016 in Alphabetical Order can be viewed below. Proposed Dates of works will be published when programmes have been agreed with the Contractors.

Scheme Location

 Ward

Surfacing Type

 Plans

Proposed Dates of works

A36 Lower Bristol Road

Westmoreland

Resurfacing

A36 Lower Bristol Road

28/09/2018 - 05/10/2018

A362 Somervale Road

Radstock

Surface Dressing

A362 Somervale Road

Complete

A367 Green Park Road

Bath

Resurfacing

A367 Green Park Road

21/10/2018 - 22/10/2018

A367 Wells Road (Phase 2)

Westfield

Resurfacing

A367 Wells Road (Phase 2)

30/08/2018 - 31/08/2018

A37 Bristol Road

Whitchurch

Surface Dressing

A37 Bristol Road

Complete

A37 Rush Hill

Farrington Gurney

Resurfacing

A37 Rush Hill

24/09/2018 - 27/09/2018

A39 Bath Road

Farmborough

Surface Dressing

A39 Bath Road

Complete

A4 Keynsham Bypass

(Phase 2) 

Keynsham

Resurfacing

A4 Keynsham Bypass 

(Phase 2)

08/05/2018 - 31/07/2018

B3110 Bath Road

Hinton Charterhouse

Surface Dressing

B3110 Bath Road

Complete

B3110 Midford Road

Midford

Resurfacing

B3110 Midford Road

Complete

B3110 Midford Road

South Stoke

Surface Dressing

B3110 Midford Road

Complete

B3114 Bristol Road

Compton Martin

Surface Dressing

B3114 Bristol Road

Complete

B3115 North Road

Timsbury

Resurfacing

B3115 North Road

28/08/2018 - 31/08/2018

B3130 The Chalks

Chew Magna

Resurfacing

B3130 The Chalks

Complete

B3130 Winford Road

Chew Magna

Surface Dressing

B3130 Winford Road

03/09/2018

Bellifants Farm including Bridge Gardens

Farmborough

Micro Asphalt

Bellifants Farm including Bridge Gardens

17/10/2018

(+/- 1 Day)

C15 Lansdown Road

Lansdown

Resurfacing

C15 Lansdown Road

Complete

C450 Norton Lane

Whitchurch

Surface Dressing

C450 Norton Lane

03/09/2018

C462 Bungays Hill

High Littleton

Surface Dressing

C462 Bungays Hill

02/09/2018

C464 Red Hill (Phase 2)

Camerton

Resurfacing

C464 Red Hill (Phase 2)

Complete

C466 Branch Road

Hinton Charterhouse

Surface Dressing

C466 Branch Road

03/09/2018

C466 Wellow Road (Phase 3)

Wellow

Recycling and Resurfacing

C466 Wellow Road (Phase 3)

Complete

C481 Lansdown Lane

Upper Weston

Resurfacing

C481 Lansdown Lane

Complete

C495 Hinton Blewett Road

Stowey

Surface Dressing

C495 Hinton Blewett Road

02/09/2018

Charles Street

Bath

Resurfacing

Charles Street

23/10/2018 - 25/10/2018

Cherry Tree Close

Westfield

Micro Asphalt

Cherry Tree Close

21/10/2018

(+/- 1 Day)

Church Lane

East Harptree

Resurfacing

Church Lane

Complete

Claverton Road

Saltford

Resurfacing

Claverton Road

30/10/2018 - 31/10/2018

Duchy Road including Prince's Street

Clandown

Micro Asphalt

Duchy Road including Prince's Street

09/10/2018 - 10/10/2018

(+/- 1 Day)

Elm Grove

Lower Swainswick

Micro Asphalt

Elm Grove

10/10/2018

(+/- 1 Day)

Englishcombe Way

Bloomfield

Micro Asphalt

Englishcombe Way

10/10/2018

(+/- 1 Day)

Great Stanhope Street

Bath

Resurfacing

Great Stanhope Street

15/10/2018

James Street West

Bath

Resurfacing

James Street West

15/10/2018 - 19/10/2018

Kipling Road

Westfield

Micro Asphalt

Kipling Road

20/10/2018

(+/- 1 Day)

Linden Gardens

Weston

Micro Asphalt

Linden Gardens

11/10/2018

(+/- 1 Day)

Little Stanhope Street and Stanhope Place

Bath

Resurfacing

Little Stanhope Street and Stanhope Place

15/10/2018

Longfellow Road

Westfield

Micro Asphalt

Longfellow Road

20/10/2018 - 21/10/2018 

(+/- 1 Day)

Manor Gardens

Farmborough

Micro Asphalt

Manor Gardens

18/10/2018

(+/- 1 Day)

Marshfield Way

Fairfield Park

Resurfacing

Marshfield Way

Complete

May Tree Road

Westfield

Micro Asphalt

May Tree Road

21/10/2018

(+/- 1 Day)

Mells Lane

Radstock

Micro Asphalt

Mells Lane

09/10/2018

(+/- 1 Day)

Mill Lane

Timsbury

Resurfacing

Mill Lane

05/11/2018

Norfolk Buildings

Bath

Resurfacing

Norfolk Buildings

15/10/2018

Park Road

Keynsham

Resurfacing

Park Road

29/10/2018 - 02/11/2018

Redfield Road

Midsomer Norton

Resurfacing

Redfield Road

Complete

Rotcombe Lane (Rotcombe Vale, Kingwell View, Parklands, and Sixpence)

High Littleton

Micro Asphalt

Rotcombe Lane (Rotcombe Vale, Kingwell View, Parklands, and Sixpence)

16/10/2018 - 17/10/2018

(+/- 1 Day)

Shaftesbury Avenue

Lower Weston

Resurfacing

Shaftesbury Avenue

Complete

Shelley Road

Westfield

Micro Asphalt

Shelley Road

20/10/2018

(+/- 1 Day)

Solsbury Way

Fairfield Park

Resurfacing

Solsbury Way

Complete

The Mead

Farmborough

Micro Asphalt

The Mead

17/10/2018 - 18/10/2018

(+/- 1 Day)

The Street

Farmborough

Micro Asphalt

The Street

19/10/2018 - 20/10/2018

(+/- 1 Day)

Tiledown (Tiledown Close, Field Gardens Road, Goldney Close, Goldney Way, and Greyfield View)

Temple Cloud

Micro Asphalt

Tiledown (Tiledown Close, Field Gardens Road, Ham Close, and Goldney Close)

12/10/2018 - 15/10/2018

(+/- 1 Day)

Tilley Close

Farmborough

Micro Asphalt

Tilley Close

18/10/2018

(+/- 1 Day)

Tunbridge Close

Chew Magna

Micro Asphalt

Tunbridge Close

11/10/2018

(+/- 1 Day)

 

 

Help us improve our website

Help us understand how people group our service.

Take part

Become a website tester

If you would like to be contacted by a member of our team to help us understand how people use our website please leave your details below.

 