Pulteney Weir repairs - advance information

 

 IN May, Bath & North East Somerset commissioned a diving survey of Pulteney Weir and the foundations of Pulteney Bridge.

 

As a result of the survey, work to repair and make the weir safer will take place in mid July.

 

Equipment storage, workers changing and rest facilities will be moved into place in the vaults under Grand Parade as from Monday, July 7, but work on the weir is not expected to start until week commencing Monday, July 14.

 

As expected, no work is needed on the foundations of Pulteney Bridge.

 

Editors Notes

 

Once we have a confirmed date for work starting on the weir we will keep you informed and do our best to help with interviews and photo opportunities.

_____________________________________

 

For comment please contact:

Councillor Colin Darracott, Executive Member for Economic Development.  Tel: 07976 732840

 

For more information contact:

Mike Gray, B&NES Project Manager Tel: (01225) 396198

 

 
Julia Dean
Press Office
Bath & North East Somerset
Guildhall
Bath BA1 5AW
 
Tel: 01225 477827
Fax: 01225 477499
 
 
* © Bath & North East Somerset Council 2004. Please read our disclaimer and privacy statement Link to Directgov – widest range of government information and services online* * Valid HTML 4.01!*