Bath & North East Somerset Council - Stabilisation Works

Stabilisation Works

Firs Field Compound
 
Firs Field Works Compound

The works compound on Firs Field was established for the project.

The worksite has now been removed as part of the reinstatement of Firs Field. 
Roadways
Steel Roadway

Roadways were required to provide safe access for Project personnel entering the mines.  Because the mines were unsafe, engineers were not able to carry out surveys or design stabilisation areas until protective roadways had been built. These underground roadways werer built by miners from steel and provide a protective ‘cage’ for engineers to survey the mine extent and mine condition and develop engineering design.  The roadways were also used to support the shuttering to contain the foam concrete which is poured in lifts and allowed to set.

These roadways were supported either by steel or timber and are required for the following reasons:

  • Protection of the underground workers
  • Ventilation
  • Drainage
  • To compartmentalise the mines so it is easier to work
  • Provide permanent routes for the bats 
  • Future monitoring and maintenance

The roadways were built according to the mine manager’s support rules, and no existing pillars were removed. The roadways were built around the pillars, so they were not straight.

The roadways in the mine were then infilled.  Due to the mines being a rich habitat for protected bat species, the design allows continued bat use by using open supports as well as structurally supporting historical shafts to improve ventilation.  

Foamed Concrete
Foamed Concrete Pour

Foamed concrete was selected as a novel solution for the large scale infilling of old mine works as part of an ongoing project for the stabilisation of the historical stone mines in Combe Down.  Over 400,000 m3 of foamed concrete was placed in the shallow underground mines, which covered more than 25 hectares. This was the single largest application of foamed concrete on a project in the UK.

Through rigorous testing, foam concrete was proven to have no significant impact on groundwater quality and provided a cured strength for a minimum 100 years support. A further advantage of this material is its ability to generate 3 times the volume of raw material during mixing e.g. 1 cubic metre of limestone dust and cement combined will generate 3 cubic metres of foam concrete. This therefore reduced tonnage and cost of raw material deliveries to site, noise, traffic and potential dust implications.

The main use of foamed concrete worldwide is in the production of precast lightweight blocks for building construction. Foamed concrete has also been used in situ as a lightweight material to infill large voids, for example disused trenches, cellars or sewers.

Foamed concrete has been proven to be both a cost effective and practical method of stabilisation which satisfies best value criteria.

Foamed concrete was selected as the prime material for infilling the mines because it is:

  • Environmentally friendly
  • Strong
  • Free flowing – the flow characteristics of the foamed concrete can be changed to take into account the different ground conditions encountered in the mines. Therefore, it flows into collapse areas with ease.
  • Versatile – it can be delivered underground more easily than normal concrete. It is also self levelling and self compacting.

Foamed concrete was also chosen as it reduced the amount of concrete base mix required while still exceeding the strength requirements (1 MN/m²). By using foamed concrete the quantity of raw materials and therefore, delivery lorries, can be reduced significantly.

Prior to stabilisation with foamed concrete, preparatory works were required to contain the material during its placement underground. Generally, the preparatory works entailed subdivision of the mine into a number of discrete zones, termed stabilisation areas.

In accessible areas of the mines, steel or timber underground roadways were constructed to provide safe access to the mine workings and defined the perimeter boundaries of the stabilisation areas. The roadways themselves were not a stabilisation method and did not provide permanent structural support. They form, however, an important part of the drainage system.

To contain the foamed concrete, re-usable plywood shuttering panels were fixed to the steel roadways, which are removed once the concrete has gained sufficient strength. Where underground access was not possible, foamed concrete infill was confined mainly by the installation of a sand or grout curtain, placed from the surface through closely spaced boreholes.

Validation drilling from the surface was carried out to ensure that the foamed concrete had adequately infilled the stabilisation area.

Foamed concrete had proven to be a viable option for mine stabilisation, especially in the unique circumstances which existed at Combe Down. The specification  developed specifically for the project  demonstrated that high quality control. The project design criteria, which was of necessity very strict, was complied with in full.

Hydrogeology Works
Borehole Drilling

Water falling onto the surface of the Combe Down Stone Mines has historically filtered through the Limestone strata and the mine voids to the layer of Fullers Earth (clay) below. This layer is impermeable and therefore the water travels along this layer following natural faults and emerges as natural springs at various points around Combe Down.

To ensure the stabilisation works did not affect this natural feature we have drilled the following types of borehole:

  1. Deep Boreholes - these are planned to supplement the limestone pillars that will act as soakaways allowing water to pass through to the clay layer, as it has historically done.
  2. Shallow Boreholes – these will be used to monitor the ground water levels above the Combe Down Stone Mines.

Deep boreholes at key locations in the village act as soakaways and shallow boreholes to monitor the ground water levels.  The data from this monitoring can then be reviewed and further action taken if deemed necessary.

Deep soakaway boreholes

The soakaway boreholes are 272mm in diameter and will be drilled to a depth 3m below the original mine floor (approximately 10-15m below ground level).  These will take approximately 1 – 2 weeks to construct.

The boreholes are securely covered with a standard manhole cover.  These boreholes will remain for a minimum of 1 year.

Shallow boreholes

The shallow boreholes are 150mm in diameter and have been drilled to the depth of the mine roof (approximately 5 – 6m below ground level). 

Monitoring

We will need to visit on occasion to take a manual water level reading.  The duration of the visit will be a maximum of 15 minutes at each location.

The frequency of access is estimated to be once a month in the long term, but initially this frequency might be higher at once a week to monitor rainfall impact.  

It is planned that monitoring will be carried out in the following months:

  • Sept 2010
  • Dec 2010
  • March 2011
  • May 2011

Following the final inspection (May 2011) they will be re-instated. 

There is a possibility that additional monitoring at some locations will be required if the results need to be verified. 

 

Contact Details for this page:
Team:
Combe Down Stone Mines
Address:
Bath & North East Somerset Council, 10 Palace Yard Mews, Bath, BA1 2NH
Phone:
01225 477200
Fax:
01225 425249
Email:
stone_mines@bathnes.gov.uk
Minicom:
N/A
Author:
Vanessa Dale