Contact:
  • Transportation Planning Team
  • Address:
    Riverside,Temple Street,Keynsham,Bristol.BS31 1LA.
  • E-mail:
    Transportation@bathnes.gov.uk
  • Telephone:
    01225 395235
  • Fax:
    01225 394335
  • Minicom:
    01225 394166
  • Page Updated:
    14/09/2007
  • Author:
    Marc Tite
A to Z Index

2 - Study Approach

2.1 Introduction

This chapter describes the study structure and the approach that has been adopted in carrying out each of the elements. It essentially follows through four hierarchical stages. Subsequent chapters describe the work associated with each of the elements. Further background information, associated with a number of study activities, can be found in the Outline Report submitted to B&NES Council in January 2002.

2.2 Study Structure

The overall approach to the study is outlined in Figure 2.1. At the heart of this structure is the interaction between two work streams:

  • A top-down visioning exercise carried out by a panel of transportation planning experts known as the Oversight Group which resulted in the development of the transportation vision and its associated strategies, plans and projects.
  • A bottom-up analysis carried out by the Core Team to ensure that the emerging strategies, plans and projects were practical and feasible.

Essentially these two work streams progressed in an iterative fashion until ‘convergence’ was achieved.

In addition, a series of stakeholder consultations was conducted to obtain a wider set of views on transport matters in B&NES. The results of these consultations formed input to both the top-down and bottom-up work streams.

The study outputs are hierarchical, and comprise of the following:

  1. A review of the overall B&NES vision and objectives;
  2. A tangible Transport Vision developed within the context of the overall vision and objectives;
  3. A Transport Strategy which defines the means of achieving the vision; and,
  4. Transport measures that are the components of the strategy.

From these outputs, it was then possible to identify those types of transport interventions, which would need to be implemented by B&NES Council over and above those already set out in the Local Transport Plan. This includes measures for the current 5-year programme and in subsequent periods over the coming 20 years.

The client team of B&NES Officers were actively involved in the study process providing information and data, reviewing outputs and taking part in consultations.

2.3 Study Process

The study process is shown in Figure 2.2. This process is centred on the four hierarchical study outputs, with iteration between the top-down and bottom-up analysis.

In practice this was achieved by an initial top-down appraisal which set out a Transport Vision for B&NES and identified the key issue of achieving modal transfer. Subsequent iteration was then required to determine a realistic strategy that could effect the necessary change. In essence this process recognised the real world constraints and the compromises which would be required.

The scale of iteration required was much greater than that originally envisaged in the Study Proposal due to the complexity of the issues. We consider that, despite the additional resources that this has taken in terms of staff inputs and study duration, this has improved the quality of the Transport Vision and Strategy.

2.4 Vision & Objectives

It was first necessary to articulate an acceptable definition of the over-arching vision and objectives for the B&NES area. This was done in the first instance through review of existing B&NES and Government policy statements. It was reinforced through a stakeholder consultation with B&NES Council Members.

2.5 Transport Vision

The Transport Vision to serve the B&NES vision and objectives was developed by the Oversight Group using a framework based on the Government’s 21 transport sub-objectives as set out in their Guidance on Methodology for Multi Modal Studies (GOMMMS). Each sub-objective was examined to determine to what degree it was achieved within B&NES, and whether it had relevance to the Vision. This was carried out with reference to local studies and data that described the existing and forecast future transport situation but was not constrained by this information. The resultant transport vision was the subject of a presentation to B&NES members, who provided further feedback.

It should be stressed that this initial ‘uninhibited’ Transport Vision leant towards an ideal situation for the community, without taking full account of behavioural and other operational constraints, which might be in conflict with each other. It was considered important that this uninhibited vision should be defined as a goal to be sought and that any compromises and trade-offs be identified as part of the subsequent stages of transport strategy development and design of transport measures.

2.6 Transport Strategy

The Transport Vision was translated into a strategy defining the broad policies and measures that would be necessary to achieve it. The initial part of this work was to identify the existing and future problems and issues associated with the Transport Vision and where necessary, to produce compromises between the elements. Local studies and data were drawn on where relevant and further analysis was conducted as necessary. The results of a wider consultation with some 250-stakeholder organisations were also examined to identify generally held policy aspirations.

2.7 Transport Measures

The outline of specific key transport measures forming part of the strategy was developed. This process drew on the assessment of problems and issues, and was developed through further technical analysis. At this stage, an assessment of future technological advances was made to determine the role of technology in executing the strategy. Specific suggestions arising from the wider stakeholder consultation were also incorporated, where appropriate.

Previous | Next

3 Page of 8