Contact:
  • Council Connect
  • Address:
    Floor 2 East, Riverside, Temple Street, Keynsham, Bristol, BS31 1LA
  • E-mail:
    CouncilConnect@bathnes.gov.uk
  • Telephone:
    (01225) 394041
  • Fax:
    (01225) 394338
  • Minicom:
    (01225) 394166
  • Page Updated:
    22/11/2008
  • Author:
    Matt Mobbs
A to Z Index
Related Documents

Charlton road – phases (PDF - 687kb) Charlton road – phases (PDF - 687kb)

For help on viewing Related Documents please refer to the Help page

My Area...


Subscribe to Inform news icon

and get local news for free.

Urban Resurfacing 2007

15/5 - This work is now complete. Thank you for your patience during these improvements.

Work Summary

The urban resurfacing contract is scheduled to begin on Sunday 28th March. Properties adjacent to or close by the works will recieve advance information letters from the Council, andthe contactor will also deliver letters prior to the works.

This information will be updated on this webpage should dates/times change due to unforeseen circumstances.  

Schedule of work  

 
Site Status Location Dates Working hours Number of work days Notes Ward
1 complete Bathford Hill Wednesday 4th April and Thursday 5th April  0930-1600 2 days Traffic lights along Bathford Hill, (and road closure of Church Street at it's junction with Bathford Hill when works to be carried out at this junction) during working hours specified. Bathavon North
2 complete Bathampton Lane Monday 26th March and Tuesday 27th March 0930-1600 2 days Daily road closures during the working hours specified. Bathavon North
3 complete Bathwick Hill Wednesday 21st March and Thursday 22nd March 0930-1600 2 days Traffic lights along Bathwick Hill during working hours specified.  St. Ann's Way will be closed at it's junction with Bathwick Hill during the works hours specified. Bathwick
4 complete Widcombe Hill Sunday 1st April and Monday 2nd April 0900-1800 on Sunday 1st April,  and 0930-1530 on Monday 2nd April 2007 2 days Daily road closures during the working hours specified.   Widcombe and Bathwick
5 complete Brassknocker Hill Sunday 18th March,   Monday 19th March and Tuesday 20th March Sunday 18th March between the hours of 0800-1800  (Southern section from Warminster Road up to the crossroads on Brasknocker Hill), and Monday 19th and Tuesday 20th March 0930 - 1600 hours  (northern section from just north of the crossroads on Brassknocker hill in the direction of Bath) 3 days Daily road closures during the working hours specified.
Dates for loop cutting and high friction surfacing between 8.00pm to 6.00am to be advised
Bathavon South
6 complete Mount Road Sunday 25th March and Sunday 15th April Sundays only, between the hours of 0900-1800 Sunday 25th March (northern section from and including Roundhill Park junction up to the triangle) and Sunday 15th April (southern section from south of Roundhill Park junction to the junction with Mount View Road) 2 days Sunday road closures during the working hours specified.
Southdown
7 complete Weston Lane Wednesday 28th March to Friday 30th March 0930-1600 3 days Daily road closures during the working hours specified. A small length of Weston Park East will be closed for a short time during the resurfacing of its junction with Weston Lane.  Weston and Kingsmead
8 complete Combe Park RUH entrances Friday 30th March,
Saturday 31st March
Sunday 1st April
Phase 1 (Main Entrance) Between 21.00 hours on Friday 30th March and 6.00am Saturday 31st, and between 21.00 hours on Saturday 31st March and 06.00 hours on Sunday 1st April 2007
Phase 2 (emergency entrance) 9.00pm Saturday 31st March to 6.00am Sunday 1st April. 
3 nights Road Closure only on Cedric Road at its junction with Combe Park during works hours specified. Traffic lights on Combe Park for the duration of the works on both Phase 1 and Phase 2 of the works during hours specified.  Newbridge
9 complete Lansdown Lane (upper section only) Tuesday 10th April to Friday 13th April (no works on the 11th due to race meeting)  0930-1500 4 days Daily road closures during the working hours specified. Bathavon North
10 complete Park Road/Foxcombe Road/Kennington Road and Warwick Road Monday 16th April to Thursday 19th April 0930-1600 4 days Daily road closures on different sections of these roads - not running concurrently.  Newbridge
11a complete

Stage 1 - Charlton Road - 'Civils' works to include pedestrian facility  improvements and traffic calming measures

(additional information)

Civils works:

Mon 19/03/07 – Sat 21/04/07
(temporary traffic signals)
Road Closure for Phase 3 only for period between Mon 16/04/07 and Sat 21/04/07


0930-1600





26 days


up to 5 days


Civils works:

Mon 19/03/07 – Fri 13/04/07 temporary traffic signals

Phase 3
Mon 16/04/07 – Sat 21/04/07 Road Closure
Keynsham
11b complete

Stage 2 -Charlton Road - Resurfacing Works

(additional information)

Resurfacing works:

Phase 2 & 4:
Sunday 22nd April (Phase 2) and
Sunday 29th April  (Phase 4)  



Phase 1, 3 & 5:
during period Mon 23/04/07 – Sat 28/04/07


0800-1800





0930-1600


2 days





6 days

Resurfacing works:

Phase 2 & 4:
Road Closure
Sun 22nd April (Phase 2) and Sun 29th April (Phase 4)


Phase 1 & 3:
Road Closures
during period Mon 23/04/07 – Saturday 28/04/07
Phase 5
Temporary traffic signals.
during period Mon 23/04/07 – Saturday 28/04/07
Keynsham

 

Charlton Road - Additional Information:

Due to the complexity of the improvement proposals and associated works, detailed plans will be on view in the window of the Council offices adjacent to the Fire Station in Temple Street. The plans for public viewing in Temple Street will be on display from Friday 16th March for approximately 10 days.

Alternatively view a plan showing the schedule of work - Charlton road – phases (PDF - 687kb)

The works commence on Monday 19th March and are expected to continue until Friday April 27th and have been broken down into two stages.

  • The ‘Civils’ works (comprising of structural changes for the pedestrian facilities and traffic calming etc) will be undertaken using temporary traffic signals, between the hours of 9.30am and 4.00pm Monday to Friday for a total of five weeks. Work will not take place between Friday 6th and Monday 9th April, Easter Bank Holiday week-end.
  • There will be a requirement for a road closure between the hours of 9.00am and 4.00pm on the section of Charlton Road which extends between the two junctions with Lays Drive, whilst the pedestrian refuge is reconstructed. This is expected to take up to 5 days, during the week commencing Monday 16th April.
  • The ‘Surfacing’ works (comprising of carriageway resurfacing, road markings, etc.) will commence on Sunday 22nd April, and are expected to be completed in 8 days – finishing on Sunday 29th April.  These works will be undertaken under temporary road closures, (excluding phase 5).

Diversion routes will be signed during the road closures, and every effort will be made to minimise noise and disruption by completing the works in as short a time as possible.

In the area of the works, pedestrian access to properties will be available at all times.  However, it should be noted that to accommodate the works, for vehicular access to properties adjacent to the works delays may be experienced, and on street parking may be suspended during works hours.  Where possible, access to adjacent properties and evening on street parking will be permitted out of works hours.