| Site |
Status |
Location |
Dates |
Working hours |
Number of work days |
Notes |
Ward |
| 1 |
complete |
Bathford Hill |
Wednesday 4th April and Thursday 5th April |
0930-1600 |
2 days |
Traffic lights along Bathford Hill, (and road closure of Church
Street at it's junction with Bathford Hill when works to be carried
out at this junction) during working hours specified. |
Bathavon North |
| 2 |
complete |
Bathampton Lane |
Monday 26th March and Tuesday 27th March |
0930-1600 |
2 days |
Daily road closures during the working hours specified. |
Bathavon North |
| 3 |
complete |
Bathwick Hill |
Wednesday 21st March and Thursday 22nd March |
0930-1600 |
2 days |
Traffic lights along Bathwick Hill during working hours
specified. St. Ann's Way will be closed at it's junction with
Bathwick Hill during the works hours specified. |
Bathwick |
| 4 |
complete |
Widcombe Hill |
Sunday 1st April and Monday 2nd April |
0900-1800 on Sunday 1st April, and 0930-1530 on Monday
2nd April 2007 |
2 days |
Daily road closures during the working hours
specified. |
Widcombe and Bathwick |
| 5 |
complete |
Brassknocker Hill |
Sunday 18th March, Monday 19th March and Tuesday
20th March |
Sunday 18th March between the hours of 0800-1800
(Southern section from Warminster Road up to the crossroads on
Brasknocker Hill), and Monday 19th and Tuesday 20th March 0930 -
1600 hours (northern section from just north of the
crossroads on Brassknocker hill in the direction of Bath) |
3 days |
Daily road closures during the working hours specified.
Dates for loop cutting and high friction surfacing between 8.00pm
to 6.00am to be advised |
Bathavon South |
| 6 |
complete |
Mount Road |
Sunday 25th March and Sunday 15th April |
Sundays only, between the hours of 0900-1800 Sunday 25th March
(northern section from and including Roundhill Park junction up to
the triangle) and Sunday 15th April (southern section from south of
Roundhill Park junction to the junction with Mount View Road) |
2 days |
Sunday road closures during the working hours
specified.
|
Southdown |
| 7 |
complete |
Weston Lane |
Wednesday 28th March to Friday 30th March |
0930-1600 |
3 days |
Daily road closures during the working hours specified. A small
length of Weston Park East will be closed for a short time during
the resurfacing of its junction with Weston Lane. |
Weston and Kingsmead |
| 8 |
complete |
Combe Park RUH entrances |
Friday 30th March,
Saturday 31st March
Sunday 1st April |
Phase 1 (Main Entrance) Between 21.00 hours on Friday 30th
March and 6.00am Saturday 31st, and between 21.00 hours on Saturday
31st March and 06.00 hours on Sunday 1st April 2007
Phase 2 (emergency entrance) 9.00pm Saturday 31st March to 6.00am
Sunday 1st April. |
3 nights |
Road Closure only on Cedric Road at its junction with Combe
Park during works hours specified. Traffic lights on Combe Park for
the duration of the works on both Phase 1 and Phase 2 of the works
during hours specified. |
Newbridge |
| 9 |
complete |
Lansdown Lane (upper section only) |
Tuesday 10th April to Friday 13th April (no works on the 11th
due to race meeting) |
0930-1500 |
4 days |
Daily road closures during the working hours specified. |
Bathavon North |
| 10 |
complete |
Park Road/Foxcombe Road/Kennington Road and Warwick Road |
Monday 16th April to Thursday 19th April |
0930-1600 |
4 days |
Daily road closures on different sections of these roads - not
running concurrently. |
Newbridge |
| 11a |
complete |
Stage 1 - Charlton Road - 'Civils' works to include pedestrian
facility improvements and traffic calming measures
(additional information) |
Civils works:
Mon 19/03/07 – Sat 21/04/07
(temporary traffic signals)
Road Closure for Phase 3 only for period between Mon 16/04/07 and
Sat 21/04/07
|
0930-1600
|
26 days
up to 5 days
|
Civils works:
Mon 19/03/07 – Fri 13/04/07 temporary traffic signals
Phase 3
Mon 16/04/07 – Sat 21/04/07 Road Closure |
Keynsham |
| 11b |
complete |
Stage 2 -Charlton Road - Resurfacing Works
(additional information) |
Resurfacing works:
Phase 2 & 4:
Sunday 22nd April (Phase 2) and
Sunday 29th April (Phase 4)
Phase 1, 3 & 5:
during period Mon 23/04/07 – Sat 28/04/07 |
0800-1800
0930-1600 |
2 days
6 days
|
Resurfacing works:
Phase 2 & 4:
Road Closure
Sun 22nd April (Phase 2) and Sun 29th April (Phase 4)
Phase 1 & 3:
Road Closures
during period Mon 23/04/07 – Saturday 28/04/07
Phase 5
Temporary traffic signals.
during period Mon 23/04/07 – Saturday 28/04/07 |
Keynsham |