Major Schemes
Publow Bridge, Publow
Refurbishment and strengthening of grade 2 listed Highway
Bridge
*THIS SCHEME WAS COMPLETED JANUARY
2006*
Start: 24th October
2005
Anticipated finish 16th
December 2005
Duration of Works: 8 weeks
Nature of Works:
The works involve the replacement of stonework and
reinforcement of the stone arch bridge to reinstate the integrity
of the structure.Following the works the existing 3 t limit will be
removed.
Reason for Works:
The existing structure in its present condition cannot take
highway loading and is currently propped to ensure that the
structure does not collapse.The propping is temporary and requires
a permanent solution.
Traffic Restrictions:
The bridge will be closed to vehicular traffic throughout the
works though pedestrian access will be maintained.