STATEMENT UNDER REGULATION 6 of the ENVIRONMENTAL ASSESSMENT OF
PLANS AND PROGRAMMES REGULATIONS, 2004
Introduction
1. On 15th July,
2004 Full Council delegated authority to the Head of Planning
Services, in consultation with the Executive Member for
Sustainability and the Environment to prepare a Statement under
regulation 6 of the draft Regulations setting out why it was not
feasible to carry out an environmental assessment [Strategic
Environment Assessment (SEA) under the European Directive
2001/42/EC] of the Bath and North East Somerset Local Plan
including Minerals and Waste Policies (“the Plan”).
2. Since that
decision Parliament has approved the Environmental Assessment of
Plans and Programmes Regulations, 2004 (“the Regulations”) and this
Statement is made under regulation 6 thereof.
The Plan timetable
3. The Plan is
at a very advanced stage. Pre-Inquiry Changes were approved in July
2004 and published for public consultation in August. The
consultation period has expired. Further pre-inquiry changes were
agreed in November 2004 and the consultation period ends in January
2005. The pre-inquiry meeting took place on 19th October, 2004 and
the public inquiry itself starts on 8th February, 2005.
4. The process
of preparing further changes to the Plan, presenting them to
Council for approval and then publishing them for public
consultation takes several months. This fact alone demonstrates
that it is not “feasible” to consider the preparation of further
changes to the Plan now. If such changes were to follow a further
environmental assessment of the Plan it is probable that any such
changes could not be prepared until 2005 and only approved for
consultation after the start of the Local Plan Inquiry. In
practice, therefore, any such changes could only be considered at a
further Modifications Inquiry.
Plan Assessment to date
5. The
preparation of the Plan has been undertaken against the background
of a series of assessments of the Plan’s impact on the environment
and sustainability issues under the Sustainable Development
Appraisal (SDA) process. Attached to this Statement is a brief
summary of the various stages at which the Plan has been assessed.
As the summary shows, there have been several stages at which an
SDA has been undertaken (1999, 2001 and 2004) and there has been
consultation on the first two of these in 2000 and 2002. The Local
Plan Inspector will have an opportunity to consider the SDA
currently being undertaken at the Inquiry in 2005.
6. The SDA
process to date has covered most of the issues which would need to
be assessed at this stage of the Plan process under the
Regulations. In these circumstances it is considered that the steps
taken by the Council to date secure substantial compliance with the
objective of the SEA Directive (2001/42/EC), which is to
“provide for a high level of protection of the environment and
to contribute to the integration of environmental considerations
into the preparation and adoption of plans and programmes with a
view to promoting sustainable development …”
Conclusion
7. It is not
practicable or feasible to undertake an SEA and then make
consequential changes to the Plan within the existing Plan
timetable (paras. 3 and 4). Accordingly, an SEA at this stage would
be merely informative and is considered unnecessary given
substantial compliance with the objective of the SEA Directive
(para. 6).
8. The
alternative of postponing the Local Plan Inquiry to enable an SEA
to be undertaken would have serious consequences for planning
throughout the district, quite apart from the more direct cost and
manpower implications of a delayed inquiry. Any additional
compliance with the Directive would be wholly disproportionate to
these adverse consequences.
9. The Council
therefore considers that it is not “feasible” to undertake an SEA
of the Plan at this stage.
David Davies
Head of Planning Services
8th December 2004
ANNEX
Strategic Environmental Assessment of the
Bath and North East Somerset Local Plan
including minerals and waste Policies
Statement under Regulation 6; Environmental
Assessment of Plans and Programmes Regulations 2004
Sustainable Development Appraisal (SDA) of Issues Report,
1999
Sustainable Development Appraisal of the Local Plan Issues
Report 1999, was conducted in November/December 1999 and public
consultation took place for a period of six weeks from March to May
2000. SDA recommendations were used to inform policy
direction in the formulation Deposit Draft Local Plan.
SDA of Deposit Draft, 2002
Sustainable Development Appraisal of the Local Plan Deposit
Draft 2002 conducted in October 2001 and public consultation took
place for a period of six weeks in January/February 2002. The
comments on the SDA were considered by the Council on 15th July
2004.
The recommendations of the SDA were reported to the 17th July
2003 Full Council meeting. The Council made responses to the
recommendations, some of which led to revisions to the Local
Plan.
SDA of Revised Deposit Draft, 2003 and Pre-Inquiry Changes
2004
This has been conducted and its conclusions and stakeholder
comments have been forwarded to the Inquiry
Inspectors.