INTRODUCTION
2.1 One of the key roles of
the Annual Monitoring Report (AMR) is to assess the implementation
of the Bath & North East Somerset Local Development Scheme
(LDS). This section addresses the advice in paragraph 4.47 of
PPS12 that AMRs should assess whether the authority:
a. has met the LDS targets and milestone or is on
target to meet them,
b. is falling behind schedule and the reasons
why, and
c. needs to update the LDS and the steps and
the timetable needed for the revision of that scheme.
BATH & NORTH EAST SOMERSET LOCAL DEVELOPMENT
SCHEME
2.2 The Bath & North East
Somerset LDS was agreed by Council in February 2005. Table 2 on
page 9 of the LDS summarises the project management programme and
milestones for the Local Development Documents. For the purposes of
Regulation 48(3)(b)(i)[1], the programme for the
preparation of LDS Local Development Documents are reproduced in
Annex 1 to the AMR
2.3 This AMR monitors the period
1st April 2004 to 31st March 2005. However, in light of the
commencement of the Act in 2004, LDS progress is assessed from its
start in October 2004. Progress on documents within the
LDS is set out in the table on the following page. In
summary, there has been no programme slippage.
2.4 The Council’s next AMR will
monitor the period April 2005 to March 2006. For
information purposes only, the table overleaf also indicates (in
italics) progress on the preparation of documents between March and
October 2005. Consideration is currently being
given to the Local Development Scheme and whether any adjustments
are needed. Of particular relevance is the timetable
for the Bath & North East Somerset Local Plan in light of the
confirmed date from the Planning Inspectorate for the dispatch of
the Local Plan Inquiry Inspector’s Report.
[1] The Town &
Country Planning (Local Development ) (England) Regulations
2004
TABLE SHOWING LOCAL DEVELOPMENT SCHEME
PROGRESS 2004-2005
(Progress since 1st April 2005 indicated in brackets)
|
LDD NUMBER |
LDS ITEM |
PROGRESS |
|
NA |
Local Development Scheme |
The only target in the period to 1st April 2005 was the
submission of the LDS to the SoS in March 2005 which was met.
(NB LDS not yet approved by SOS)
|
|
NA |
Annual Monitoring Report
|
No LDS targets in the period to March 2005
(Progress between March and October 2005:
Draft AMR submitted to GOSW in Sept 2005)
|
|
LDD1 |
Bath & North East Somerset Local
Plan
|
Public Local Inquiry opened in February 2005 as programmed.
(Progress between March and October 2005:
· Local Plan Inquiry took
place February 2005 to May 2005
· Inspector’s Report now
expected May 2006)
|
|
LDD2 |
Statement of Community involvement
|
No LDS targets in the period to March 2005.
(Progress between March and October 2005:
Commencement of SCI in October 2005 as programmed)
|
|
LDD3 |
Bath City-wide character appraisal
|
Pre-production survey and sustainability appraisal underway
between September 2004 and March 2005 as programmed.
(Progress between March and October 2005:
SPD adopted in August 2005 as programmed)
|
|
LDD4 |
Streetscape Manual
|
All stages completed and LDD adopted in April 2005 as set out in
the LDS.
|
Page last updated 13/01/2006