Section 2

LOCAL DEVELOPMENT SCHEME PROGRESS

INTRODUCTION

2.1      One of the key roles of the Annual Monitoring Report (AMR) is to assess the implementation of the Bath & North East Somerset Local Development Scheme (LDS).  This section addresses the advice in paragraph 4.47 of PPS12 that AMRs should assess whether the authority:

a.    has met the LDS targets and milestone or is on target to meet them,

b.    is falling behind schedule and the reasons why, and

c.    needs to update the LDS and the steps and the timetable needed for the revision of that scheme.

BATH & NORTH EAST SOMERSET LOCAL DEVELOPMENT SCHEME

2.2      The Bath & North East Somerset LDS was agreed by Council in February 2005. Table 2 on page 9 of the LDS summarises the project management programme and milestones for the Local Development Documents. For the purposes of Regulation 48(3)(b)(i)[1], the programme for the preparation of LDS Local Development Documents are reproduced in Annex 1 to the AMR

2.3      This AMR monitors the period 1st April 2004 to 31st March 2005.  However, in light of the commencement of the Act in 2004, LDS progress is assessed from its start in October 2004.   Progress on documents within the LDS is set out in the table on the following page.  In summary, there has been no programme slippage.

2.4      The Council’s next AMR will monitor the period April 2005 to March 2006.   For information purposes only, the table overleaf also indicates (in italics) progress on the preparation of documents between March and October 2005.    Consideration is currently being given to the Local Development Scheme and whether any adjustments are needed.   Of particular relevance is the timetable for the Bath & North East Somerset Local Plan in light of the confirmed date from the Planning Inspectorate for the dispatch of the Local Plan Inquiry Inspector’s Report.

[1] The Town & Country Planning (Local Development ) (England) Regulations 2004

TABLE SHOWING LOCAL DEVELOPMENT SCHEME PROGRESS 2004-2005

(Progress since 1st April 2005 indicated in brackets)

LDD NUMBER

LDS ITEM

PROGRESS

NA

Local Development Scheme

 

The only target in the period to 1st April 2005 was the submission of the LDS to the SoS in March 2005 which was met.  

 

(NB LDS not yet approved by SOS)

 

NA

Annual Monitoring Report

 

 

No LDS targets in the period to March 2005

 

(Progress between March and October 2005:

Draft AMR submitted to GOSW in Sept 2005)

 

LDD1

Bath & North East Somerset Local Plan

 

 

Public Local Inquiry opened in February 2005 as programmed.

 

(Progress between March and October 2005:

·       Local Plan Inquiry took place February 2005 to May 2005

·       Inspector’s Report now expected May 2006)

 

LDD2

Statement of Community involvement

 

 

No LDS targets in the period to March 2005.

 

(Progress between March and October 2005:

Commencement of SCI in October 2005 as programmed)

 

LDD3

Bath City-wide character appraisal

 

 

Pre-production survey and sustainability appraisal underway between September 2004 and March 2005 as programmed.

 

(Progress between March and October 2005:

 SPD adopted in August 2005 as programmed)

 

LDD4

Streetscape Manual

 

 

All stages completed and LDD adopted in April 2005 as set out in the LDS.

 