Combe Down Stone Mines Land Stabilisation Project

 Homepage & Project Updates

 Welcome

Combe Down Stone Mines

The Combe Down Stone Mines Project is a major project by Bath & North East Somerset Council to stabilise abandoned limestone mine workings in Combe Down and preserve the Health & Safety of the area. The aim of the Project is to remove the current threat to life and property of those living, working in and travelling through the Combe Down area.

In doing this, the Project will ensure that the internationally recognised heritage, wildlife and environmental properties of the area are conserved for future generations.

This website provides further information on  project progress and environmental issues related to the Project. If your questions are not answered then you can contact the Project Team by email, telephone or in person at the Information Centre.

We hope that you enjoy using this website and will find the information useful. If however, you have any suggestions on how we could improve our website, please email the Project Team on stone_mines@bathnes.gov.uk

Works Progress 2008

 

Since the last newsletter, the project has now progressed well. As of September 427,584m3 of concrete has been poured, which equates to 93% of the total forecast concrete volume for the project. 14,695m of roadway has now been constructed which equates to 99%.

See below for Stabilisation Area Status drawing.

Springfield Quarry
Since our last newsletter works to stabilise the mine at Springfield Quarry have commenced and are progressing well.

Hydrogeology Works
Hydrogeology testing has recently begun following the infilling of most of the mine workings. A water bowser is used to pour water through a series of test boreholes to imitate the infiltration of rainfall into the soil and rock horizons above the stabilised areas. The aim of this test work is to understand the way in which the soil and the rock both hold and transmit water. This will enable the engineers to develop proposals to mitigate any increased risk of flooding.

Archaeology
A planning application (08/00977/REG03) was approved that recognised there is no safe way to leave open the areas of archaeological interest within the mine and protect the land above. This approval gave permission for these areas to be infilled with foamed concrete and infilling is almost complete.

The archaeology has been recorded to the highest level with methods including time-lapse photography and digital fly-throughs. These will be published and included as part of the interpretation at the end of the scheme.

The archaeology team are now assessing all finds and recorded data and are also interested in any related items that the public many have. Should you have any artefacts that you believe may be of interest to the archaeologists for recording or photographing, please contact the Project Team.

Property Condition Surveys
Final Property Condition Surveys are now underway in those areas where works are complete. White Young Green will make contact with each landowner at the time required. Should you own a garage in the village which is in a separate location to your residence, please inform WYG as all buildings will require a close out survey.

Verification / Topping up

As part of the process of completion of the concrete bulk infill into the stabilisation areas, surface verification drilling is required to establish that the concrete has reached the required level within the mine.  This will require drilling throughout the village in gardens, drives and roads alike. Should a void be identified from the drilling works, surface topping up will take place.

The project is now at the stage where this verification of the infill is increasing. We will therefore need to gain access to gardens and drives more frequently. It is important to the project programme that this can be concluded quickly to allow works to progress and we trust we can count on your continued cooperation with this.

Should we require access for such drilling works, we will send you a letter in advance of the works, and then make contact by telephone to arrange an appointment for the contractor and engineer to visit prior to drilling.

 

News Update

Church Road now Open

Church Road is now OPEN between the Belmont Road and Tyning Road junctions.

We are awaiting the results of underground works to determine whether a closure of the section of Church Road between Tyning Road and Monkton Combe Pre-Prep School will be needed. 

 

Dvd's for sale

During the underground visits at the beginning of the Project, a dvd was shown giving a background to the Land Stabilisation Project and the mines at Combe Down. Images are shown of miners working underground and information is given on the various methods of stabilisation. The DVD lasts around 10 minutes and was commissioned by the national regeneration agency, English Partnerships. Should you wish to purchase a copy, please send a cheque for £5 made payable to Bath & North East Somerset Council to 10 Palace Yard Mews, Bath, BA1 2NH