Stabilisation Programme
Phase II - Main Scheme
The Main Scheme commenced April 2007. The Main Scheme
works continue the concrete infill and roadway construction, but
also focus on bat,
archaeological and drainage issues. Investigation of the
mine margins continues as part of the Main Scheme to determine the
extent of the Firs and Byfield mine complex.
The compound at Firs field increased in size for the Main Scheme
and there are now 250 personnel working on site. Following
the tender process and approval from central government,
Hydrock have been
appointed as the main scheme contractors. Also on site are
Scott Wilson Mining (Project Consultants) and Davis
Langdon (Project Management support)
As part of the completion of stabilisation, surface verification
is required to establish that the concrete has reached the required
levels within the mine. This requires drilling on the surface in
various locations in the village, including gardens, drives and
roads. Should a void be identified by the drilling works surface
topping up will take place. The project is now at the stage
where the requirement for this verification drilling is
increasing.
Completion of the Main Scheme construction is scheduled for
2010.